Concrete bags vs bulk

Free interactive tools with clear assumptions, practical results and a private project workspace.

Your estimate

My project workspace

Saved estimates stay in this browser. Export a CSV for your records; no account required.

Calculator library

How to use the featured calculator

Enter slab dimensions and extra allowance, then compare whole bags with the supplier's billable bulk quantity. Include short-load fees and rental or labor costs in the appropriate fields.

Worked example

A 10 × 10 ft slab 4 in thick has about 33.33 cubic feet before allowance. At 8% extra, it requires 36 cubic feet, or 60 bags if the stated yield is 0.6 cubic feet per bag.

Before using your estimate

This is a material estimate only; it does not determine reinforcement, slab thickness, site preparation or structural suitability.